WinSport's snowmaking is capped at 40 per cent until the new feeder main is in service

The City has granted WinSport overnight snowmaking capped at 3 million litres a night, while the Bearspaw South Feeder Main connection stays on schedule.

· 4 min read · HOC Calgary Desk
WinSport's snowmaking is capped at 40 per cent until the new feeder main is in service
★ FREE NEWSLETTER
Get the best of Calgary Region in your inbox

The day's top stories, food & events — every morning at 7. Unsubscribe anytime.

WinSport can now make a small amount of snow overnight, but only about 40 per cent of its full snowmaking capacity. That limit holds until the new Bearspaw South Feeder Main is fully in service and the system adjustments are made, expected in mid to late December.

The City granted WinSport's request to make snow when the weather allows, capped at 3 million litres of water per night. The permission can be withdrawn at any time if demand rises or the system runs into trouble. The City says its priority is making sure there's enough water for the most critical needs, and that current demand and system stability leave enough water to help WinSport without risking supply.

The water is rationed for a reason. The Bearspaw South Feeder Main failed in June 2024 and again on December 30, 2025. The second break brought two weeks of restrictions. Restrictions took effect Nov. 4, and the City says they are set to lift in about a week and a half. Calgary is relying primarily on one water treatment plant during the roughly four-week shutdown for the connection.

WinSport is a not-for-profit that relies on early-season snowmaking to build its snow base for the winter. Its staff, community and school programming, athletes and sport organizations are all feeling the delay.

Where the work stands: the connection is on track and entering its third week. Pipe is complete at the Shaganappi Pump Station, with valve chamber installation ongoing. At 89 Street and 33 Avenue, crews are working around the clock, a new steel T-Joint has been placed and welding is ongoing. At 83 Street and 33 Avenue, excavation is exposing existing distribution pipes and the schedule is being maintained. At Parkdale Boulevard and Memorial Drive N.W., pipe installation is complete at all five locations and backfilling and surface rehab are underway.

Water demand is running below the daily target of 500 million litres. Saturday's demand was 476 million litres and Sunday's was 490 million litres. Calgary, Airdrie, Chestermere, Strathmore and the Tsuut'ina Nation are all keeping demand down.

What it costs: council approved a $609.5 million capital budget increase in March, bringing the total cost tied to the Bearspaw feeder main to $439 million. That includes $381 million for the replacement project and $222 million for a new 22-kilometre feeder main running north from the Bearspaw plant. The increase is mostly financed through debt repaid by water rates. There is no change to 2026 rates, but water rates go up 14 per cent in 2027, about $17 more a month, and ratepayers in Airdrie, Chestermere, Tsuut'ina Nation and Strathmore share that increase. Council also approved $21 million more for water operations staffing.

The bigger picture: Calgary's 2005 "30-in-30" plan, updated in 2016, cut per-capita water use by 30 per cent while the city grew significantly. Those efficiency gains have plateaued since 2016, and overall water demand keeps rising. The 2026 Calgary Water Efficiency Plan targets a 20 per cent reduction in per-capita demand by 2040.

the Water Utility Oversight Board holds its first meeting in December 2026, and the replacement pipe is expected in service that month. Until then, WinSport's snowmaking stays at about 40 per cent of capacity, within the 3 million litre nightly cap.

Source documents
newsroom.calgary.ca/water-demand-stays-low-work-on-schedule-as-connec...
newsroom.calgary.ca/water-restrictions-take-effect-nov-4-as-bearspaw-...
newsroom.calgary.ca/calgarys-updated-water-efficiency-plan-approved-b...