LRT east extension to Orléans still not open as Ottawa finishes more testing
Full-line testing on Line 1 starts Nov. 22, but passengers still can't ride past Blair Station and no opening date is set.
The day's top stories, food & events — every morning at 7. Unsubscribe anytime.
Riders still can't take Line 1 past Blair Station, and the Orléans extension has no opening date. The city says more work is needed before passengers can ride it. Full-line testing starts Sunday, Nov. 22, between Tunney's Pasture and Trim stations.
It's the first time 23 trains will run the full route, about every four and a half minutes at peak times. The goal is to test vehicles, schedules, staffing and reliability before pre-trial running begins. Rick Leary, general manager of Rideau Transit Maintenance, wrote in a Nov. 18 memo to council that software upgrades were completed Sunday, Nov. 15.
The line was shut down that morning so sub-contractor Hitachi could reprogram the train-control software. Leary said the system was run "to ensure the successful upgrade" and is "now ready to proceed with additional system testing." Separately, he said additional work is still required to improve the reliability of the traction power substation, and that OC Transpo will monitor it before pre-trial running begins.
The city has cited "deficiencies" found during performance testing and commissioning. The extension has been delayed since January, when a "spalling" issue forced dozens of Line 1 trains offline for repairs. Pre-trial testing was forecast for early October and was pushed to mid-November to accommodate the software work.
Pre-trial running takes about a week, followed by 21 consecutive days of trial running, then five to 10 days of certifications and approvals before passengers can ride. That puts a passenger opening at least five weeks after pre-trial running starts. OC Transpo expects to update council in December on when pre-trial running will begin.
What are the specific deficiencies the city found during commissioning, and do they affect the opening timeline?
What is the revised date for pre-trial running, and will council get that answer in December as promised?
Why was the traction power substation still unreliable after months of work?
We'll update this story as answers emerge.