O-Train East condition monitoring system 80% ready for trial operation
Out-of-service trains are now running between Blair and Trim to test the system. OC Transpo expects enough vehicles by the end of August to begin pre-trial and trial running.
The day's top stories, food & events — every morning at 7. Unsubscribe anytime.
Final readiness activities are underway for the O-Train East extension as OC Transpo prepares for trial running, and customers should expect to see more out-of-service trains operating between Blair and Trim stations each week.
These test runs are part of exercising the system, identifying challenges, and addressing issues ahead of customer service, OC Transpo said. The condition monitoring system — being installed to allow more trains to run during daily service — is 80 per cent ready for trial and was begun in June. OC Transpo is on target to have enough vehicles by the end of August.
OC Transpo is working with Rideau Transit Group (RTG) and East-West Connectors, the East Extension constructor, to determine a schedule for pre-trial and trial running. This work is key to building confidence that the system is operating as intended.
Customers can also expect Blair platform to be closed at certain times, with advance notification. Shortly before trial running begins, trains will operate between Tunney's Pasture and Trim stations, with customers required to disembark at Blair Station. Passenger information displays will show Trim as the final destination. OC Transpo staff will be present at Blair to support customers through the transition. A technical briefing will be held before trial running to provide more detailed information.
The facts
What percentage ready is the O-Train East condition monitoring system?
The condition monitoring system is 80 per cent ready for trial operation.
When does OC Transpo expect to have enough vehicles for trial running?
OC Transpo is on target to have enough vehicles by the end of August 2026.
Which stations will out-of-service trains run between during testing?
Out-of-service trains are running between Blair and Trim stations to test the system.
What will happen at Blair Station when trial running begins?
Blair platform will be closed at certain times with advance notification, and passengers will be required to disembark at Blair Station before trains continue to Trim.