Mississauga's mayor says 'bring it on' as two real estate firms appeal city's data centre pause
Prologis and Montcrest are challenging the city's one-year moratorium on large data centres at the Ontario Land Tribunal, and Mayor Alvin Tedjo says he is ready to fight.
The day's top stories, food & events — every morning at 7. Unsubscribe anytime.
Mississauga's new mayor says he is ready to fight two real estate companies that have appealed the city's one-year pause on large data centres. "I say, bring it on," Alvin Tedjo told reporters in his first one-on-one interview since taking office.
The moratorium, passed unanimously in September, applies citywide to data centres with energy demands of 10 megawatts or more, roughly enough electricity to power 10,000 homes. It runs for one year from September 16, and council can extend it to no more than two years in total. The city says the pause gives it time to study guardrails around energy, water and noise impacts.
Prologis, a U.S. company, filed its Ontario Land Tribunal appeal on November 4. It had been pursuing a 40-megawatt facility on Tenth Line, south of Highway 401, beside an Ikea warehouse and close to an electrical substation. The nearest residential neighbourhood is about a kilometre away. A Prologis spokesperson, Mattie Sorrentino, said in an emailed statement that "multiple companies have filed appeals" and that "the bylaw is poorly conceived without justification for its restrictions or consideration of the consequences for businesses seeking to invest in Mississauga." The company argues the city already has a project-by-project planning process.
Montcrest Asset Management, a Toronto private equity real estate firm, is appealing over its Tahoe Centre property in northeast Mississauga. The site is zoned for employment uses that include data processing, and Montcrest says the bylaw's concerns don't apply to that land. Spokesperson Melissa Fernandez said the company takes the concerns seriously and will work within the regulatory process for any future proposals.
Tedjo said the moratorium lets the city set the conditions for data centres, and that residents have made clear they don't want American real estate investment trusts deciding what gets built in their communities.
The city's policy review is due to report to council later this year, with a recommendation expected in spring to summer 2027.