Trans Mountain finishes capacity boost two months early, reaching up to about 980,000 barrels a day

Trans Mountain finished its chemical additive project two months early, lifting pipeline capacity up to 980,000 barrels per day from the Edmonton area.

· 3 min read · HOC Edmonton Desk
Trans Mountain finishes capacity boost two months early, reaching up to about 980,000 barrels a day
File photo: Stephen Andrews / Pexels
★ FREE NEWSLETTER
Get the best of Edmonton Region in your inbox

The day's top stories, food & events — every morning at 7. Unsubscribe anytime.

The Crown corporation said Friday, Nov. 27, when it released third-quarter results, that it had completed work to increase its pipeline's throughput two months ahead of schedule. Drag-reducing agent, a chemical additive that cuts friction inside the line, is the mechanism behind a gain of up to about 10 per cent, which brings capacity to 980,000 barrels per day. Crude moves from the Edmonton area to Burnaby, B.C., through the system.

The Canada Energy Regulator approved the project on June 5. It involves drag-reducing agent units at existing pump stations on Line 1 and Line 2. The units sit inside existing fence lines and need no new land, so the extra oil moves through pipe that is already in the ground.

The pipeline shipped 840,000 barrels per day on average in the third quarter, up from 777,000 in the same three months of 2025. About 60 per cent of that went to the Westridge Marine Terminal, where tankers sail across the Pacific to Asian customers. The rest went to British Columbia and Washington state.

Trans Mountain reported net income of $132 million for the quarter, up from $127 million, on revenues of $825 million, up from $765 million.

The regulator approved new firm capacity on Sept. 29. That capacity is expected to take effect in stages starting Jan. 1, 2027. Bids in the open season that offered it were significant but are not quantified here.

The expanded line cost more than $34 billion and started up in May 2024. This quarter, $551 million was paid to the federal government, and $1.45 billion has been paid so far this year in interest payments, dividends and return of capital distributions. Officials with the federal government and Trans Mountain have said they are in no hurry to return the pipeline to private hands. Trans Mountain said it began confidential information sessions with potential Indigenous partners in October.

Trans Mountain is also leading development of Pacific Link, a proposed pipeline of one million barrels per day that would largely follow the same route and end at a port in Delta, B.C. The Government of Canada listed Pacific Link as a project of national interest on Oct. 1.

The St'at'imc Nation and T'Sou-ke First Nation filed a joint application earlier in November to quash Ottawa's decision.

The facts

How much capacity does the Trans Mountain pipeline now have after the chemical additive project?

The Trans Mountain pipeline can now carry up to about 980,000 barrels per day after its drag-reducing agent project raised capacity by up to about 10 per cent. Trans Mountain finished that work two months ahead of schedule.

How much crude did the Trans Mountain pipeline ship in the third quarter of 2026?

The Trans Mountain pipeline shipped 840,000 barrels per day on average in the third quarter of 2026. That was up from 777,000 barrels per day in the same three months of 2025.

How much net income did Trans Mountain report for the third quarter of 2026?

Trans Mountain reported net income of $132 million for the third quarter of 2026. That was up from $127 million in the same period a year earlier.

When did the Canada Energy Regulator approve the drag-reducing agent project for Trans Mountain?

The Canada Energy Regulator approved the Trans Mountain drag-reducing agent project on June 5, 2026. The project added units at existing pump stations on Line 1 and Line 2.