Steveston playground gets $118K monkey bars 15 months after $2.2M rebuild

Monkey bars and climbing features went into Steveston Community Park this fall, with the Steveston Community Society putting in $83,000 and about $35,000 coming from city funding.

· 2 min read · HOC Vancouver Desk
Steveston playground gets $118K monkey bars 15 months after $2.2M rebuild
★ FREE NEWSLETTER
Get the best of Metro Vancouver in your inbox

The day's top stories, food & events — every morning at 7. Unsubscribe anytime.

The monkey bars and climbing features went into Steveston Community Park this fall, about 15 months after the rebuilt playground reopened on June 24, 2025. The work followed feedback: a pop-up open house on Nov. 22, 2025, run by the city and the Steveston Community Society, showed strong interest in monkey bars, climbing structures and more challenging features.

The enhancement cost about $118,000. The Steveston Community Society put in $83,000 and about $35,000 came from existing city funding. One resident asked how much more taxpayers would pay for the work; the city's Dammy Ogunseitan answered in an emailed statement: "After the playground reopened.. The city heard from community members who wanted more challenging play options, especially for older and more adventurous children."

The rebuild itself was $2.2 million, approved in the city's 2023 budget. Including the September additions, total spending on the playground since 2024 is about $2.3 million, mostly city money. A $30,000 Tire Stewardship BC grant helped pay for the recycled rubber play surface.

The new work connects the existing play features. One swing set was moved within the playground to make room. The rest of the equipment and surfacing wasn't touched.

The on-site work took less than one week in September. Earlier scheduling had the work starting the week of September 8, expected to take three to four weeks, with the shipwreck structure, wobble boards and belt swing set fenced off, though most of the playground stayed open.

The society started planning the renewal in 2014, and council approved a concept plan in 2017 after public engagement. The first playground on the site went up in 1942, after the society bought the property and donated it to the municipality.

What we're still asking

How much of the existing $35,000 city money came from the 2023 rebuild budget, and was it separate?

Are any further enhancements planned for the park?

We'll update this story as answers emerge.